3KM header background image

Three Kids Mine:
Revitalizing a Neglected Historic Site

Cleanup Status

Under the careful oversight of the Nevada Division of Environmental Projection (NDEP), the cleanup began in May 2024 and is anticipated to be completed by Fall 2025. Key milestones include:

Asbestos removal and disposal started in May 2024 and was completed in February 2025.
Excavation of over 2 million cubic yards of tailings started in June 2024 with containment completed in May 2025.
Cleanup of demolished concrete and impacted soil started in August 2024 and is scheduled to be completed by the end of June 2025.
Waste rock reclamation started in July 2024 and is scheduled to be completed by the end of 2026.
The former Hydro Pit has been backfilled with excavated tailings, waste rock, and preparation for the 60mm liner has begun.
The Hulin Pit and A-B Pit will be backfilled with waste rock and demolished concrete.
Three Kids Mine image

Dust Control and Air Monitoring

NDEP Logo

Communications

NDEP is the lead agency overseeing the cleanup of the former Three Kids Mine site. You can stay informed by visiting their website. There you will find site clean up documents, including air monitoring reports, inspection reports, progress reports, as well as community update mailers and frequently asked questions.

three kids mine image

Contact Us

The Three Kids Mine Story

Scroll to Top